Hi all, was just wondering if you could help. My cousin is doing a new build with abode homes and they still have not completed the dwelling two and a half years after initially starting. She was 55 days late on the first progress payment which she paid $1300 damages to the builder and the building was commenced a couple of weeks later. From reading her contract the building should be completed 200 days after commencement with up to 70 days misc, 55 days late on progress payment and 21 days in which the builder has to recommence work. So in total that is 346 days. Therefore they are over 500 days late on the build. She has a liqudated damages clause of $250 per week which the builder denied having to pay because she was late on her progress payment. So my question is, is she still eligible for the liquidated damages????sorry for the long winded story!!!!